What changes can and cannot I make to the project design and when do I need to request approval for a change?
Without a request for approval of a change, but with proper justification in the interim or final report, the following can be implemented (no contract amendment or new decision required): transfers within other operating costs or within personnel costs, transfers between other operating x...